Proposed Wind Farm at Fullabrook Down
 

Home
 

About CAWT
 

Why CAWT objects
 

Public Inquiry
 

Fund Raising
 

Government policy
 

CAWT responses
 

Links

PUBLIC INQUIRY

The completion of evidence and official site visit ended 4 weeks of the enquiry on
22nd December 2006.  The final summing up takes place in The Guildhall Barnstaple on 11th/12th January 2007, commencing at 10:00 am.

We understand that the final decision could take anything between three and nine months.

Our advocate Geoffrey Sinclair has done an excellent job for us and it is now obvious that it would have been an extremely difficult task without his help.

Many thanks to all who supported us in so many ways and in particular for your donations and fundraising efforts without which we would not have been able
to employ Geoff.

 

View the OPENING STATEMENT
which Geoffrey Sinclair, the CAWT advocate
made at the public enquiry.